Independent Power Producer
Establishment Process
Disclaimer: this is an indicative timeline and is subject to change as we are dealing with various government departments and state-owned entities. Outcome and Approvals are not Guaranteed.
Below is a high-level outline of the process to establish an IPP and obtain the relevant licenses that are required before funder engagement and EPC process commencement.
PRE-FEASIBILITY & SPV ESTABLISHMENT
WEEK 1
WEEK 2
Week 3
Week 4
Week 5
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT & APPROVAL
WEEK 6-9
WEEK 9-12
Week 12-16
Week 12-16
Week 16-24
TECHNICAL GRID APPLICATION & AUTHORISATION
WEEK 6-12
WEEK 13-16
Week 17-24
Week 24-28
Week 29-40
WEEK 41-45
WEEK 46
Week 47-70
Week 72-82
Week 83-104